€200m Alexandra Basin Redevelopment (ABR) Project By Dublin Port Company

Dublin Port Company has lodged a planning application with An Bord Pleanála for its Alexandra Basin Redevelopment (ABR) Project.

The application is being made under the Planning and Development (Strategic Infrastructure) Act and follows a twelve month consultation with industry, government, customer and community stakeholders.

[rev_slider Surety]

 

Local information centres will be open over the coming weeks with details of the proposal plans on view.

The ABR Project involves an application to An Bord Pleanála for permission for phased redevelopment work on some of Dublin Port’s existing infrastructure. Some 42% of Dublin Port’s berths (3km of the port’s 7km) will be lengthened and deepened and the 10km channel from Dublin Bay to the East Link Bridge will be deepened. It is the first large scale project under Dublin Port Company’s Masterplan 2012-2040, a framework for the future development of Dublin Port with reference to economic and trade developments set in the context of EU, national, regional and local development plan policies.

The ABR Project will cost an estimated €200 million and Dublin Port Company has the financial resources to fund the project. The engineering works will take place on a phased basis and are expected to take five years to complete, supporting some 200 construction related jobs in the process. It is further estimated that the growth in volumes which the project will facilitate will result in 320 jobs being created annually between 2012 and 2040.

Commenting on the application for Dublin Port Company’s Alexandra Basin Redevelopment (ABR) Project, Eamonn O’Reilly, Chief Executive of Dublin Port Company said, “Dublin Port Company’s ABR Project will give us the infrastructure, capacity and versatility needed to futureproof Dublin Port, catering for larger sized vessels and increased trade volumes as Ireland returns to economic growth. Dublin Port Company is committed to carrying out this project within our current footprint, re-developing and utilising existing port lands in the most efficient way possible, while financing the project from our own resources.

“We have engaged with Government, business and industry stakeholders, customers and local communities over the past year to help shape today’s planning application. The public can view the proposal in detail, meet members of the project team at public information days from 25th – 27th March and learn about all aspects of the project over the coming weeks”, he added.

Submissions or observations on the application may be made to An Bord Pleanála at 64 Marlborough Street, Dublin 1, by 7th May 2014.

The project comprises engineering redevelopment works in the Alexandra Basin and in the Berth 52/53 Basin. Some of the proposed development works will include*:

Proposed Purpose

ALEXANDRA BASIN

Deepening and reconfiguration of quay walls at North Wall Quay Extension (937m total length), including the relocation of the North Wall lighthouse.

Extension of Alexandra Quay (130m).

Rebuilding of existing, life expired quay walls in the remainder of the Alexandra Basin West (aggregate length of 1,200m).

New 273m long Ro-Ro jetty with Ro-Ro berths on either side.

To increase Dublin Port’s berth capacities using the port’s existing footprint so as to accommodate larger freight and passenger ships at multi-purpose berths.

The multi-purpose berths will cater for a range of uses, including freight and cruise.

BERTHS 52/53

Construction of a new 300m river berth at Berth 52/53 and two new mooring jetties.

To provide the port with two river berths for the largest future Ro-Ro ships.

DEEPENING THE PORT

Dredging of the Liffey Channel and approach to the port to a depth of -10m (Chart Datum) from east of the East Link Bridge to the Dublin Bay Buoy, a distance of about 10km in total.

To provide a deeper channel for larger vessels including, ferry and cruise ships. Source: Afloat.